Riviera Beach demonstration and pilot plants

- Scale
- $2M + $6Mtwo plants, built and commissioned
- Place
- Riviera Beach, FL
- Years
- 2020–2022
- Role
- Senior Project Engineer; project lead, design through startup
Two microwave-plasma plants that turn natural gas into hydrogen and acetylene. Both were delivered on budget and on schedule, in a building certified to hold explosive gases and high-voltage equipment.
Full story and key facts
- Challenge
- A new process had to become a working, permitted facility. The building would house explosive, flammable gases next to novel high-voltage equipment running above 20 kV (20,000 volts).
- What he did
Took both plants through every stage: permitting, front-end engineering design (FEED, the early design that fixes scope and cost), process-safety reviews (HAZOP), detailed design, fabrication, factory acceptance testing (proving equipment at the maker’s shop before it ships), construction, commissioning and operations.
The ~$2M demonstration plant was designed and built in-house. The ~$6M pilot plant was executed with engineering-procurement-construction (EPC) contractors.
- Result
- Secured UL certification and a certificate of occupancy. Both plants were delivered on budget and on schedule. The demonstration plant finished ahead of schedule and ran successfully on its first startup, with more than 99% uptime at full product purity.
- ~$2M demonstration plant, designed and built in-house
- ~$6M pilot plant, executed with EPC contractors
- UL certification and certificate of occupancy
- >20 kV high-voltage equipment
- >99% uptime at full product purity
- Successful first startup, ahead of schedule